With a US$559 Million Investment, San Jorge Puts Mendoza on the Global Copper Map

4 minutes
With a US$559 Million Investment, San Jorge Puts Mendoza on the Global Copper Map
With a US$559 Million Investment, San Jorge Puts Mendoza on the Global Copper Map
Compartir:

The environmental impact report (EIA) adjustment for **PSJ Cobre Mendocino**, formerly known as San Jorge, has been presented. The project entails a **US$559 million investment** and could become the **first mining project in Mendoza** to be incorporated into Argentina’s **Large Investment Incentive Program (RIGI).** _**Por Panorama Minero**_
PSJ Cobre Mendocino, previously San Jorge, has initiated the **environmental evaluation process** to obtain an **Environmental Impact Declaration (DIA)**, a requirement for the construction of this copper project located in **Uspallata, Las Heras, Mendoza.**
The **EIA adjustment** follows a restructuring of the company leading the project. **PSJ Cobre Mendocino** is now backed by **Zonda Metals GmbH (Switzerland)** and **Grupo Alberdi (Argentina)**. Grupo Alberdi recently entered the mining sector through the exploration of **Cerro Amarillo**, a copper project in **Malargüe, Mendoza.**
Without considering additional drilling that may extend its lifespan, the **production phase** is projected to last **16 years**, with the potential to expand up to **27 years**. Over its initial 16-year lifespan, PSJ is expected to **produce an average of 40,000 tons of fine copper per year**. ### **RIGI and Project Implementation** PSJ requires a total **investment of US$559 million**, including **US$461 million for construction** and **US$81 million for operations**. With these investment levels, it is the **first mining project in Mendoza eligible for the Large Investment Incentive Program (RIGI).**
Company representatives emphasized that **"copper is a key resource for the global energy transition"** and that **PSJ is positioned as a strategic project contributing to the responsible supply of this essential metal.**
The **Mendoza Chamber of Mining Entrepreneurs (CaMEM)** highlighted the province’s current vision of **integrating mining into its economic matrix**. They also stated that **PSJ could accelerate the development of a sustainable mining industry**, especially given the **recent advances in exploration policies**, including the establishment of the **Malargüe Western Mining District**.
If the project obtains **DIA approval**, **PSJ would be the first of eight copper projects** currently under discussion to move into production. As a **mid-sized project**, it would require a **construction period of 18 to 24 months**.
_"By mining standards, this is an extremely fast timeline. For Mendoza, it represents a valuable opportunity to start diversifying its economy and promoting sustainable economic developments that generate real jobs. It opens a highly promising window of opportunity for the province,"_ said **Guillermo Pensado**, President of **CaMEM**.
The company estimates that the project will generate approximately **3,900 jobs during construction** and **2,400 jobs during operations** (including **800 direct and 1,600 indirect jobs**). ### **Mining Systems and Production Levels** PSJ is located within **Estancia Yalguaraz**, covering **8 discovery claims** with a total area of **9,984.37 hectares**.
Given that the **mineralized body is close to the surface and contains disseminated ore**, **open-pit mining** is the most **technically and economically viable** extraction method. The **ore processing** will include **crushing, grinding, flotation, thickening, and filtering** to produce a **dry concentrate with 25% copper content.**
The **PSJ porphyry system** presents a **vertical mineralization gradient**, transitioning from **primary mineralization at depth** to an **upper enriched zone**. The deposit consists of **copper and gold oxides and sulfides**, with an average **copper grade of 0.47%** and **gold grade of 0.191 g/t**. The final product will be a **dry Cu-Au concentrate** with an **average Cu content of 25% and trace amounts of Au**.
The **processing circuit** will include **three-stage conventional crushing** followed by **flotation using standard reagents**.
**Laboratory-scale tests** on enriched and primary ore composites indicated **90% copper recovery** and **74% gold recovery** from the primary deposit.
The processing plant is designed with a **capacity of 10 Mt/a**, yielding an **average of 151,000 t/a of copper concentrate**, with a **maximum output of 241,000 t/a**. Only one product will be obtained from the treatment process: a **copper concentrate with minor gold content**.
Average production during the mine’s lifespan is estimated at **40,000 tons of fine Cu per year**, with peak production reaching: - **70,000 tons in year two**, - **59,000 tons in year three**, - **50,000 tons in year four**. It is estimated that PSJ will produce **an average of 18.9 t/h of concentrate**, reaching peak values of **36.6 t/h** at certain times, with a **copper content of approximately 25% and 9% moisture**. ### **Environmental Evaluation Process** The **submission of the EIA adjustment** for PSJ marks the **first step toward obtaining the Environmental Impact Declaration (DIA).** In Mendoza, this approval is granted by the **Directorate of Environmental Protection** and the **Directorate of Mining**.
The report will be **reviewed by specialized agencies**, which will then request **input from other relevant institutions** through sectoral reports.
If the **DIA is approved**, it must then be **ratified by the provincial legislature** through both chambers.
According to **Article 3 of Law 7.722**, **all environmental approvals (DIA) for exploration or production must be ratified by legislators**. The permit only becomes effective **once it is approved by a simple majority vote and published in Mendoza’s Official Bulletin**.

Publicado por: Panorama Minero

Categoría: Noticias

¿Querés recibir noticias del sector y de las iniciativas de Panorama Minero?


Suscribite a nuestro boletín.

Illustrative image for the news: Mendoza Seeks to Teach the Value of Minerals Through Urban Mining | Panorama Minero

Mendoza Seeks to Teach the Value of Minerals Through Urban Mining

A new competition launched by Mendoza’s Mining Directorate invites students to produce content on electronic waste and the circular economy. The initiative uses urban mining as a starting point to explain that minerals are part of everyday life and can be recovered once an electronic device reaches the end of its useful life.

Leer más
Illustrative image for the news: Cauchari-Olaroz: Lithium Argentina Announces Closing of New US$220 Million Debt Facilities | Panorama Minero

Cauchari-Olaroz: Lithium Argentina Announces Closing of New US$220 Million Debt Facilities

The Cauchari-Olaroz lithium brine operation, developed through Minera Exar S.A., has completed the closing of US$220 million in new unsecured debt facilities, further strengthening its financial position and expanding its financing flexibility as it continues advancing Stage 2, the expansion project designed to increase production capacity by an additional 45,000 tonnes per year of lithium carbonate equivalent (LCE).

Leer más